Casework and trim is currently being installed.
Painting and concrete floor sealer is completed. Light fixtures are
being installed on both floors. Renovation work should be complete in
early January.Plumbing, HVAC and electric rough-in installation
is in process. Masonry wall construction has been completed. Studio
casework has been delivered, and the dust collection system has been
installed. All block fill and painting is beginning.
Plumbing, HVAC and electric rough-in work is in
process. Masonry walls are being installed.
Mechanical rough-in work is in progress.
Concrete has been poured for the new second floor, and final demolition
is being completed. New masonry walls are also being installed.Demolition of the existing space began
in early August and was completed in three weeks. The structural steel,
which is a critical path item for this project, is being installed.
Once structural steel is installed, the general contractor will begin
construction work.
Structural steel contractor bidding has
begun with bids due May 31. The remaining construction documents are
being reviewed by the building committee for the final time prior
to the bidding of the general contractor package. Additionally, the
moving and storage of existing equipment is being coordinated in preparation
of the start construction.
Currently, the project is in the 50 percent construction documents
phase. In this phase, the specifications for the project are generated
to meet the requirements of the user groups. Plans are being developed
to assist in the move of the current users to other locations. Additionally,
final plans are being made for the storage of all materials in the
space.
The design development phase of this project will be completed by
the end of March, with the construction documents phase beginning
in April.